Foundation work for new construction of a large bridge

West bypass, Rosenheim

Constructing the 11.5 km west bypass in Rosenheim: For this project, Bauer Spezialtiefbau was tasked with foundation work for the new construction of a large bridge over a railway line. No easy task, since the execution of the mixed foundation was very elaborate: In total, roughly 11,500 m² of pressed sheet pile wall, 15,000 m of vertical drains and 253 large-diameter bored piles were constructed up to a depth of 50 m. The particular challenge: the unique construction soil on site. Starting from a depth of roughly 2 m to 5 m is a soil known as Rosenheim marine clay. This was an extremely sensitive soil stratum which offered a very low load-bearing capacity and high water content. A large project with many challenges.

Facts about the project
Company :

BAUER Spezialtiefbau GmbH 

Location :

Rosenheim, Germany

Project name :

West bypass, Rosenheim

Project partner :

Menard GmbH

Period :

February 2019 to May 2020

Services :

Foundation work (mixed foundation), pressed sheet pile wall, vertical drains, large-diameter bored piles

Press release :

Bridge foundation in Rosenheim marine clay

253 Großbohrpfähle bis in eine Tiefe von 50 m für den Bau der Westtangente Rosenheim von Bauer Spezialtiefbau
Bauer Spezialtiefbau installs 253 large-diameter bored piles up to a depth of 50 m for the construction of the Rosenheim west bypass
11.500 m² gepresste Spundwand für den Bau der Westtangente Rosenheim von Bauer Spezialtiefbau
Bauer Spezialtiefbau installs 11,500 m² of pressed sheet pile wall for the construction of the Rosenheim west bypass
Gründungsarbeiten für den Neubau der Großbrücke in Rosenheim von Bauer Spezialtiefbau
Bridge foundation in Rosenheim marine clay by Bauer Spezialtiefbau