Dike rehabilitation Mündelheim

Improving the sealing

To protect Mündelheim against future flooding, a cut-off wall will be constructed along a new dike. For this project, Bauer Spezialtiefbau was tasked with executing a Mixed-in-Place cut-off wall in the subsoil of a new planned dike. One particular challenge was the subsoil composed of sand, silt and gravel. Works encompassed an approx. 24,800 m² cut-off wall with a thickness of 55 cm and a maximum depth of 21 m, executed using an RG 25.

Facts about the project
Company :

BAUER Spezialtiefbau GmbH

Location :

Mündelheim, North Rhine-Westphalia

Project name :

Mündelheim Dike

Period :

August 2019 to March 2020

Services :

Mixed-in-Place cut-off wall

Reference letter :

Mündelheim Dike on the banks of the Rhine