Foundation work for South Bank Quay
The South Bank Quay is part of the Teesworks Freeport project, which secured £107 million in the UK Investment Bank’s first ever investment. With immediate access to the River Tees and the North Sea, the 1 km quay will provide global firms with 500 acres of development land. Our experts from Bauer Technologies were appointed to undertake the piling and foundation works for the project. Specifically, Bauer Technologies, constructed the 156 nos King Piles required to form the new quay wall. A complex project with many challenges to contend with, including adverse weather conditions, with often high winds effecting the many lifting operations. The ground conditions were also challenging, requiring long temporary casings to be installed for the king pile installation. But for our team no problem.
Despite the many challenges and the scale and tight schedule of the works, the project, which commenced on the 17 January 2022, was completed successfully on the 17 March 2023, on time, on budget and to the full satisfaction of the client.
BAUER Technologies Limited
Teesside
South Bank Quay
17 January 2022 to 17 March 2023
King Piles, Sheet pile infill wall, rotary bored piles, rotary bored bearing piles, static pile load test, Sheet pile anchor wall
Do you have any questions?
To discuss your project geotechnical requirements, please contact our team.
10 Ducketts Wharf
South Street
Bishops Stortford
Hertfordshire
CM23 3AR United Kingdom