Foundation work for SRT (Red Line) Bang Sue – Talingchan
The SRT Red Line is a significant railway project aimed at enhancing transportation connectivity in Bangkok. The Bang Sue – Talingchan section required extensive foundation work, including the installation of 1,136 bored piles by Thai Bauer. Our experts installed piles with diameters ranging between 800 and 1,800 mm and up to 58 m deep. The project also featured two barrette piles, each measuring 1.2 x 2.5 m and extending 55 m deep. The construction work was completed in 2 years, laying a solid foundation for the railway's future impact on Bangkok's transportation network.
Thai BAUER Co. Ltd.
Bangkok, Thailand
SRT (Red Line) Bang Sue – Talingchan
April 2009 to May 2011
Bored Piles, Barrette Piles
From Bang Sue to Talingchan
Are you starting a project?
Get in touch with us.
Two Pacific Place, 17th Floor
142 Sukhumvit Road
Bangkok 10110
Thailand