Foundation work for 28 Chidlom Project
The 28 Chidlom Project in Bangkok involved extensive foundation work executed by Thai Bauer. The project included the installation of 22 barrette piles measruing 1,000 x 2,800 mm with a depth of 55 m. Additionally, 30 bored piles of 800 mm diameter, 146 bored piles of 1,000 mm diameter, and 7 bored piles of 1,200 mm diameter, all reaching a depth of 55 m, were constructed. Our expert's work also involved the installation of 2,326 m² of diaphragm walls with a thickness of 1,000 mm and a depth of 26 m. The construction was successfully completed between November 2016 and March 2017.
Thai BAUER Co. Ltd.
Bangkok, Thailand
28 Chidlom Project
November 2016 to March 2017
Diaphragm Wall, Bored Piles, Barrette Piles
Solid Foundations