Excavation pit Construction for Cairo Metro Line 3 Phase 4

Strengthening 4 Metro Stations

For the fourth phase of Cairo Metro Line 3, Bauer Egypt was commissioned to carry out essential foundation and soil treatment works. This phase involved the construction of four stations – Heliopolis, Alf Maskan, Shams Club and El Nozha – along with four annexes, a cut-and-cover section, and an exit shaft. Our expert’s scope of work included the installation of 72,800  m² of diaphragm walls, the construction of 105 barrettes with steel posts, and the application of soil treatment through a horizontal grout blanket across three stations. Additionally, jet grouting and TAM were used to address hard points, ensuring the stability and durability of the underground structures. The project was completed efficiently, contributing significantly to the expansion of Cairo’s metro infrastructure.

Facts about the project
Company :

BAUER EGYPT S.A.E. Specialised Foundation Contractors

Location :

Cairo, Egypt

Project name :

Cairo Metro Line 3 Phase 4

Period :

2015 to 2016

Services :

Diaphragm Walls, Barrettes, Jet Grouting 

72,800 m² of Stability

Are you starting a project?

Get in touch with us.

BAUER EGYPT S.A.E. Specialised Foundation Contractors

197, 26 July Street
El Mohandeseen
Cairo