Foundation work for South Bangkok's Power Plant Replacement
The South Bangkok Power Plant Replacement Phase 1, located in Samutprakarn, involved key foundation work carried out by Thai Bauer. The project required the installation of 12 pilot bored piles and anchor piles, each with a diameter of 1200 mm and a depth of 20 m. Furthermore, 616 working bored piles with the same specifications were installed to support the structure. Our experts completed the construction for this phase in four months, ensuring a stable foundation for the power plant's expansion.
Thai BAUER Co. Ltd.
Samutprakarn, Thailand
South Bangkok Power Plant Replacement Phase 1
July to December 2017
Bored Piles
Powering Up